Microsoft Project For Dummies. Cynthia Snyder Dionisio
Чтение книги онлайн.

Читать онлайн книгу Microsoft Project For Dummies - Cynthia Snyder Dionisio страница 19

Название: Microsoft Project For Dummies

Автор: Cynthia Snyder Dionisio

Издательство: John Wiley & Sons Limited

Жанр: Программы

Серия:

isbn: 9781119858645

isbn:

СКАЧАТЬ project summary task represents the highest (least detailed) level of information and is often simply the title of the project, such as New Product Rollout. When you tell Project to display the project summary task, every task in the project falls under it in the outline, as shown in Figure 3-2.

Snapshot of the project summary task.

      © John Wiley & Sons, Inc.

      FIGURE 3-2: The project summary task.

The summary task rolls up all data from other tasks into one line item. Thus, the project summary task’s duration reflects the duration of the entire project. From a monetary angle, the project summary task’s total cost reflects the total costs for the entire project. Figures such as these can be handy to have at your fingertips — and that’s one value of a summary task.

      As you build your project, you can easily create a project summary task yourself (indent other tasks beneath it) or use a Project feature to generate one automatically at any time — even after you build all the phases of your project. To have Project automatically display a project summary task, follow these steps:

      1 In the Gantt Chart view, select the Format tab in the Gantt Chart Tools context tab group.

      2 In the Show/Hide group, select the Project Summary Task check box.

      As you can see in Figure 3-2, Task 0, Desert Rose Security, is the project summary task. Notice the bar for the project summary task on the chart is gray and that the bars for other summary tasks are black.

      

If you’re confused about the length of your summary task, remember that the summary task duration is the difference between the earliest task start date and latest task end date. However, nonworking days aren’t counted in the summary task duration. The length of the summary task, therefore, equals the number of days of work over the course of the subtasks, not the number of calendar days between the start of the first task and end of the last.

       You can quickly view totals for the project at a glance in the columns of data in Gantt Chart view and other views.

       You can place a link to your project summary task in another project so that all data for one project is reflected in another. For example, Desert Rose Security is one project in the Desert Rose Community Program. If there are projects for each of the four neighborhoods in the community, you can create one schedule for security and one for each of the four neighborhoods. Then you can easily create a master schedule for the whole program by linking to the project summary tasks in each of the projects.

      In Chapter 2, I show you how to outdent and indent tasks to create the WBS and the project outline. In this section, I show you additional ways to move tasks as well as collapse and expand tasks.

      A maxim of project management says that things change: Tasks that you thought you could complete early can’t happen yet because money, people, or materials are in short supply. Or a task that you thought you couldn’t start until next July gets bumped up in priority when your customer changes their mind (again) about deliverables. Because of this changeability, when you enter tasks in a project outline, odds are that you’ll need to move those tasks around at some point. You should understand that moving a task can change its outline level, so you’ll need to check your outline level for tasks that you move and adjust it as necessary using the indent and outdent features.

      Moving tasks with the drag-and-drop method

      If you ask me, drag-and-drop is to computing what the remote control is to television. It’s a quick, no-brainer method of moving stuff around in software that just makes life simpler. Here’s an example:

      To move a task up and down with the drag-and-drop method, follow these steps:

      1 Display a column view, such as Gantt Chart view.

      2 Select a task by clicking its task ID number.Simply click and release; don’t hold down the mouse button.

      3 Click and drag the task to wherever you want it to appear in the outline.A gray “T-bar” line appears, indicating the new task position.

      4 When the gray line is located where you want to insert the task, release the mouse button.The task appears in its new location. If you want the task to be at a different level of the outline, you can now indent or outdent it as needed.

      

If you move the parent task, all the child tasks, and all the relevant information — such as start, finish, duration, cost, and so on — come with it.

      Moving tasks with the cut-and-paste method

      Dragging and dropping works fine in most cases, but in very large projects — with a few hundred tasks or more, for example — it’s easier to cut and paste instead of scrolling through hundreds of tasks to find the exact location you want to move your tasks to.

      In a larger outline, it’s best to use the cut-and-paste method to move tasks:

      1 Select a task by clicking its task ID number.

      2 Click the Cut button in the Clipboard group on the Task tab.The task is removed from its current location and placed on the Windows Clipboard.

      3 Scroll to display the location where you want the task to appear.

      4 Click the task after which you want to insert the task.

      5 Click the top part of the Paste button, also on the Task tab.

      If you want to insert a copy of a task in a project outline, you can follow the preceding steps and click Copy rather than Cut.

      

If you’re cutting and copying only a single cell and not a whole task, click in the cell rather than clicking the task ID number.

      

You can also use the standard Microsoft shortcuts — Ctrl+C to copy, Ctrl+X to cut, and Ctrl+V to paste.

      Remember in elementary school when your teacher made you create an outline to organize your work? The outline helped you arrange content and allowed you to focus on different levels СКАЧАТЬ