Microsoft Project For Dummies. Cynthia Snyder Dionisio
Чтение книги онлайн.

Читать онлайн книгу Microsoft Project For Dummies - Cynthia Snyder Dionisio страница 18

Название: Microsoft Project For Dummies

Автор: Cynthia Snyder Dionisio

Издательство: John Wiley & Sons Limited

Жанр: Программы

Серия:

isbn: 9781119858645

isbn:

СКАЧАТЬ the Look In list, locate and select the file to which you want to insert a hyperlink.

      6 Click the OK button.The link text is inserted, and a hyperlink symbol appears in the Indicator field. You can simply click that link symbol to open the linked file, or right-click and choose Hyperlink, then choose Open Link, or Open in New Window.

Snapshot of linking a file.

      © John Wiley & Sons, Inc.

      FIGURE 2-10: Linking a file.

      

Good organizational practice suggests that you create a folder for your project where you save your Project file, any linked files and supporting documents, such as the Charter, risk register, and other items. You can create a new folder from within the Save As dialog box by clicking the New Folder button.

      Becoming a Task Master

      IN THIS CHAPTER

      

Creating summary tasks and subtasks

      

Moving tasks

      

Collapsing and expanding tasks

      

Creating recurring tasks

      

Creating milestones

      

Deleting tasks and making tasks inactive

      

Entering a task note

      The foundational unit in a project schedule is the project task; everything starts with it. After you identify and document your tasks, you can work with resources, dependencies, costs, durations, and other elements.

      To be an effective task master, you need to be nimble in managing your tasks: Determine how to summarize work with a summary task, move work around, start and stop work in the middle of a task, and do all kinds of other tricks that help your schedule reflect what you want to happen on your project.

Snapshot of Summary tasks and subtasks.

      © John Wiley & Sons, Inc.

      FIGURE 3-1: Summary tasks and subtasks.

      In Figure 3-1 you can see that the Walls and Entry Gates summary tasks show all their subtasks. The summary tasks of Equipment, Asset Management, and Operations Readiness have hidden subtasks.

      All information about a family of tasks is rolled up into its highest-level summary task. Therefore, any task with subtasks has no timing or cost information of its own: It gathers its total duration and cost from the sum of its parts.

      This roll-up functionality is cumulative: The lowest-level task rolls up to its parent, which might roll up into another summary task, which rolls up (for example) into a project summary task. Any task with tasks below it gets its duration and cost information from a roll-up of its subtasks, no matter how deeply nested it may be in the hierarchy.

      

When you need to reorganize an outline, you can move a summary task and all its subtasks come with it, regardless of whether it’s expanded.

      How many levels can you go?

      You have no practical limit on how many levels of tasks you can create in an outline. Project enables you to indent to more levels of detail than you’ll need for all but the most complex schedules. Remember, though: At some point, you have to deal with assigning timing and resources to each of these tasks and then track their progress. Too much detail can make your schedule difficult to manage. For example, if your project is a few months long, you don’t want to track to a level where tasks last only a few hours. Best practices suggest that you always set up your schedule to the level to which you want to manage your team — typically, business (working) days or weeks.

      For longer projects, you can schedule by using rolling wave planning, a method of progressively elaborating the amount of detail for near-term work and keeping at a higher level any work that’s further out. For example, if you have a two-year project, you may have the first three months planned out in detail, the next three months at a higher level, and the remainder of the project schedule showing only milestones and key deliverables. As you progress through the project, you start to add more detail for six months and beyond. A good rule of thumb is to keep a good amount of detail for 90 days out.

      

Rolling wave planning isn’t an excuse to add scope; it’s only the elaboration of existing scope.

      The project summary task

СКАЧАТЬ