Overall Equipment Effectiveness. Robert Hansen C.
Чтение книги онлайн.

Читать онлайн книгу Overall Equipment Effectiveness - Robert Hansen C. страница 13

Название: Overall Equipment Effectiveness

Автор: Robert Hansen C.

Издательство: Ingram

Жанр: Здоровье

Серия:

isbn: 9780831191153

isbn:

СКАЧАТЬ 2.1. In such cases, the speed factor should be limited to 1.0 (if rate is higher than ideal) with proper notification for inventory control.

       The nomenclature in italics and basic formulas are stated in “Introduction to TPM” by S. Nakajima1.

image image image

      Figure 2-4, the completed summary sheet from section 2.4, provides input values for the three methods used to compute the following OEE values. The basic information from the practice production report (section 2.3) is used each time.

      Total Time = 240 blocks × 10 min/block = 2400 min

      Ideal (Theoretical) Rate = 4 units/min (15 sec cycle time)

      Assume a 3.5 percent waste or 96.5 percent yield for normal production activity.

image

      Then, Actual Units Produced =

image

      Given that 160 units were contaminated and, therefore, designated as No Good (NG),

      Number of Good Units Produced = (4680 − 160) × 0.965 = 4362 Good Units

image

      Loading Time = Total Time − Excluded Time =2400 min − 570 min = 1830 min

image

      From above, Total Units Produced = 4680

image

      Performance Efficiency = 1 × Operating Speed Rate = 1 × 0.873 = 0.873

      OEE = Availability × Performance Efficiency × Quality Rate

      = 73.2 percent × 0.873 × 0.932 = 59.6 percent

      Note: Nakajima doesn’t calculate TEEP

      Scheduled Time = Total Time − Excluded Time = 2400 − 570 = 1830 min

      Runtime = 1000 + 340 = 1340 min

image
OEE = Availability × Speed Rate × Quality Rate
= 73.2 percent × 0.873 × 0.932 = 59.6 percent
image
TEEP = Asset Utilization × Speed Rate × Quality Rate
= 55.8 percent × 0.873 × 0.932 = 45.4 percent

      Accurate OEE can be determined by multiplying Theoretical Cycle Time, Number of Good Units, and Schedule Time. An event time record is not required, except for detailing profitable OEE opportunities. Recall from above that 4362 Good Units were produced and should be equal to the amount of product transferred. If all product is transferred without reduction for off specification units in your area, then modify the transferred amount by historical quality levels. Theoretical Cycle Time is known to be 4 units/min, and Scheduled Time is 1830 min., a known production value.

image

      This result is exactly the same as that reached by methods 1 and 2.

image

      This section is key to understanding the factors used to compute OEE. It demonstrates that true OEE can be found by several approaches. Furthermore, it reconciles with plant output as seen in the next section.

       2.6 Reconciliation and Loss Analysis

      Once OEE is calculated, the various losses are computed from the summary sheet information. Analyzing these losses will help you identify areas that have major opportunity for improving OEE. Obviously, improvement in any area will help OEE. However, the greatest opportunities for OEE improvement are those areas with large losses.

      OEE is not the only factor behind company productivity. Therefore, the different potential programs must be ranked for their overall benefit. For example, some industries may have specific quality or financial considerations that must be incorporated into their lists of priorities. All programs should not only be evaluated for their anticipated benefits, but also be congruent with the goals of the company. When completed, they should be measured for evidence of their success. Evaluating the trends of most key parameters will usually identify the impact of a program before and after its completion. Chapter 5 discusses a value fulcrum, a concept that can help rank nearly equal projects on a reactive to proactive scale.

      When setting goals, you should link throughput improvement with desired progress of other parameters. Take this step when you initially assess the current baselines of all parameters. It often takes creativity to define the relationship between parameters. However, by clearly communicating the desired outcomes, the priorities are understood and supported by the entire community. I recommend that you focus on no more than three key projects at a time and complete them as quickly as possible. Do not let your resources be diffused on a multitude of jobs. Good progress will occur if you select and eliminate the right limiters.

      In general, the loss analysis step is a point where synergy between OEE and other key parameters occurs. During this step, the detailed equipment performance records will help identify significant root cause limiters. Cross-functional teams properly trained in objective problem solving and focused on the areas of large losses often make breakthrough gains in OEE improvement. Detailed observations that are provided by an effective equipment performance system database will be of assistance. Once the key root cause limiters are identified and eliminated, significant improvement in performance will occur.

СКАЧАТЬ