The 2017 FIDIC Contracts. William Godwin
Чтение книги онлайн.

Читать онлайн книгу The 2017 FIDIC Contracts - William Godwin страница 21

Название: The 2017 FIDIC Contracts

Автор: William Godwin

Издательство: John Wiley & Sons Limited

Жанр: Юриспруденция, право

Серия:

isbn: 9781119514657

isbn:

СКАЧАТЬ Contractor has raised the matter quickly enough might give rise to argument.

      3.2.6 Clause 3.5/3.4 Sub‐paragraph (b)

      If an instruction is not stated to be a variation, and the Contractor does not consider that it is, but does believe that the instruction fails to comply with applicable laws or will reduce the safety of the works or is technically impossible, then under sub‐paragraph (b) of clause 3.5/3.4 he must, again before commencing any work related to the instruction, immediately give a notice to the Engineer/Employer with reasons for his view. The same seven‐day response is required from the Engineer/Employer confirming, reversing or varying the instruction, with the Contractor being bound to comply with the terms of the Engineer's /Employer's response, provided the notice is given in time.

      The procedure for obtaining the parties' agreement or issuing a determination if no agreement is forthcoming has become far more detailed and structured than in the 1999 editions of the contracts, with greater emphasis on consultation involving the parties and the Engineer/Employer's Representative. The procedure is the same in all the 2017 contracts, although, as noted above, it is set out in clause 3.7 of the 2017 Red and Yellow Books and clause 3.5 of the Silver Book. As also noted above, the process of agreement or determination covers not merely claims but applies whenever the conditions of contract require the Engineer or Employer's Representative to proceed to determine any matter or claim.

      In what follows clause references will be to clause 3.7 of the 2017 Red and Yellow Books and the contract administrator will be referred to as ‘the Engineer’.

      3.3.1 Consultation

      If agreement is achieved within the time limit for agreement under clause 3.7.3, the Engineer must give a notice of the agreement to both parties, stating on its face that it is a notice of their agreement (which they must sign) and including a copy of it. If no agreement is achieved within the time limit, or both parties advise the Engineer that no agreement can be achieved within that time, whichever is the earlier, then the Engineer is to give a notice to the parties accordingly. He must then immediately proceed under clause 3.7.2 to a determination.

      3.3.2 Engineer's Determination

      Under clause 3.7.2 the Engineer must make a fair determination of the matter or claim, in accordance with the Contract, taking due regard of all relevant circumstances. Within the time limit set out in clause 3.7.3 (see next section), he must give a notice to both parties of his determination. The notice must state on its face that it is a notice of the Engineer's determination and describe the determination in detail, with reasons and detailed supporting particulars.

      3.3.3 Time Limits

      Clause 3.7.3 sets out the time limits for the various stages in the agreement or determination process.

      The Engineer must give notice of agreement, if agreement is reached, within 42 days, or within whatever other time limit he proposes and the parties agree, after:

      1 in the case of a matter to be agreed or determined which is not a claim, whatever date of commencement of the time limit for agreement may be stated in the relevant Contract clause; or

      2 where there is a claim by either party, for relief other than under clause 20.1(a) or (b),8 the date the Engineer receives a clause 20.1 notice from the claiming party; or

      3 where there is a claim under clause 20.1(a) or (b), the date the Engineer receives:a fully detailed claim under clause 20.2.4,9 orwhere there is a claim of continuing effect under clause 20.2.6,10 an interim or final fully detailed claim, as appropriate.

      Thus time limits reinforced by deeming provisions apply in order to seek to ensure both that adequate consultation takes place between the parties, facilitated by the Engineer, and that, if despite that process agreement cannot be achieved, the matter or claim is resolved within a defined period by the Engineer's determination, failing which it may be referred to a DAAB.

СКАЧАТЬ